R. E. Lee & Son, Inc. was the low bidder on this parking garage project that was constructed for Water Street Development. This project included 2 acres of sitework and construction of the parking garage adjacent to a CSX railway. This parking garage includes six levels totaling 692 parking spaces and 19,000 sf of retail space located in Downtown Charlottesville.
Project Highlights
Project Team
Owner: Water Street Development
Architect: VMDO, Architects
Contractor: R. E. Lee & Son, Inc.
Project Delivery System
Competitive Bid; Build
Construction Schedule
Completed in 450 calendar days.
Construction Type
Structural Pre-Cast Concrete with Caisson Foundations