St. Anne’s-Belfield School / Lee Duval Hall, Charlottesville, VA

R. E. Lee & Son, Inc. was selected as the General Contractor for renovations and additions to this student residence building. Work included asbestos abatement, demolition and re-construction of dormitory rooms, and additions to the exterior. Work was completed over one summer so that school activity and enrollment was not affected.

Project Highlights

Project Team

Owner: St. Anne’s-Belfield School / Rev. George Conway
Architect: Daggett & Grigg Architects / Bill Daggett
Contractor: R. E. Lee & Son, Inc. / Stan Binsted

Project Delivery System

Negotiated / Design/ Build

Construction Schedule

90 days. No interruption to school schedule.

Construction Type

Interior and exterior renovation